Construction is underway at the Pfeiffer Road and Deerfield Road intersection, converting the four-way stop to a single-lane roundabout. In 2022, construction consisted of utility work, including installing a new gas and water mains. In addition, a new storm sewer was installed, along with temporary asphalt pavement to the south side of Pfeiffer Road and the west side of Deerfield Road.
Construction is scheduled to resume this month, and the completion date is August 2023.
The upcoming construction timeframe for the remainder of the work is as follows:
March – April Construction of the roundabout on the northeast corner of the intersection.
April – May Construction of the roundabout on the northwest corner of the intersection.
May – July Construction of the roundabout on the southwest and southeast corners of the intersection. This phase will involve the closure of Deerfield Road south of the intersection for approximately six weeks. Traffic south of the intersection will detour to Montgomery Road.
July – August Final construction activities and transition of the intersection from a four-way stop to a single-lane roundabout.
The above timeframe is approximate and might change based on weather and other factors. Two-way traffic on Pfeiffer Road and Deerfield Road will be maintained except as mentioned above and when the final surface course of asphalt is placed towards the end of the project. Traffic delays are expected during construction, so please take an alternate route. We appreciate your patience during this important project!