Quantcast

West Hamilton News

Friday, November 22, 2024

2022 Street Project Update

16

City of Madeira issued the following announcement on Apr 4.

2022 Street Project Update:

1) Madeira Hills Drive/Willowhollow Drive.  The contractor intends to begin curb removal this week (April 4th) on Madeira Hills Dr. Residents will be notified by a “door hanger”. Willowhollow will be started in mid to late April as it is next on the schedule.

2) Osceola, Rita, Iuka, Rathon, Sanoma Drive/Avenue. Storm Water Repairs are to begin the first week in May with curb work and final pavement to be completed in mid-July.

3) Fowler (between Euclid and S. Timberblane)/Mar Del. Milling and pavement work to be accomplished beginning the first and second week of May.

4) Kenview. Milling and paving to be completed weeks of May 9th and 16th.

5) Jethve/Berwood/Homart.  No change to the previously announced schedule.  Water main work to begin the week of April 11th and paving work to be completed mid to late July.

Original source can be found here.

ORGANIZATIONS IN THIS STORY

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate

MORE NEWS